SignCube: further wrapup duties


Completed
  • Demo screencasts for app and website usage
    • Hardcoded subtitles as appropriate
  • Additional project outcome: application for Young Social Pioneers alongside Enable Development
    • Extension of tech + education application

Ahead
  • Write up summary of SignCube experiences for Enable Development blog
  • Caption final presentation video
Ahead (ongoing)
  • Report Report Report
  • Polish up app

Sunday, 22 March 2015

SignCube Phase 1 completion


Completed
  • Mobile app documentation
  • Final presentation delivered to EWB, Enable Development
    •  Recorded for submission to Business Victoria
  • Discussion with Huy re: thoughts on Phase 1
  • Initial planning for next phase of project
    • Team composition

Ahead
  • Create screencasts of website, app being used to submit to BV
  • Begin structuring report format
  • Follow up with Ros Rimington

Thursday, 12 March 2015

SignCube Phase 1 wrapup



Completed
  • Preparation for handover process
    • Project documentation: overview, decisions made, problems encountered, meeting summaries, recommendations, contacts etc
    • Technical documentation: functionality, classes, resources, future development plan etc
    • Removal of dead code
    • Extra code commenting and TODOs
    • Code moved into appropriate packages
  •  App progress frozen for documentation
    • View function triggers toast
    • Simpler yes/no on review
    • Progress bar to indicate encode, upload progress
    • Issues with encoded video fixed
Ahead
  • Complete documentation (esp recommendations)
  • Meet with Enable Development to discuss future role more fully
  • Presentation to Huy, Julian, more tbc